MENDOCINO CO., 11/29/26 — If you drive through Hopland, plan on another month of roadwork on Highway 101. Caltrans had told the town the job would be done in November. Now it says Dec. 31, and that’s if the weather holds.
Until then, the closed sidewalks and the 25 mph speed limit stay, Caltrans spokesperson Manny Machado said in an email Wednesday.
“Rain, storms, low temperatures, or unforeseen field conditions could delay the work,” Machado wrote.
The job is giving downtown new sidewalks, curb ramps and pavement. Crews still have sidewalks to tear out and rebuild on both sides of the highway. After that they’ll pull out the concrete barriers, grind down the road, repave it and put up signs.
The lane stripes go on last. If the weather is wrong for the permanent ones, crews will paint temporary stripes and come back in the spring, Machado said.
The job is costing more, too. O.C. Jones & Sons of Berkeley won it with a bid of $6.4 million, state records show. The contract now stands at $9.3 million, Machado said, about $2.9 million over the bid.
“This amount is expected to increase as Caltrans approves additional change orders before project completion,” Machado wrote. A change order is a change to a contract after it’s signed.
Machado said the changes paid for traffic control and for work that came up in the field, such as replacing what’s under the road, replacing drainage pipes and adjusting utilities. He didn’t say what each one cost.
Businesses in town are open, Caltrans says. Drivers may wait up to 10 minutes during work hours.
Questions? Call Caltrans at 707-994-9362 or email [email protected].