Construction on W. Gobbi Street in Ukiah in July 2024. (Google Earth via Bay City News)

UKIAH, CA., 4/1/25 — Major street reconstruction and utility replacement on Main, Gobbi, and Perkins streets, continues. The project is planned to wrap up (finally!) this summer, but winter rains have caused many delays. 

Below, please find the latest updates from the City of Ukiah: 

West Gobbi street paving rescheduled due to weather

Utility replacement and concrete work is complete on West Gobbi Street between State and Dora streets. Paving was scheduled for the first week of April to coincide with Ukiah school district spring break, but because of the rains, the work is now rescheduled for early summer. More information will be provided once a new schedule has been set.

Main Street

Water main tie-ins on Main Street are nearly complete but have also been delayed by the weather. There will be a temporary disruption to traffic in the Main Street/Perkins intersection to complete the tie-in, likely late next week (weather dependent). Once the remaining tie-ins are complete, water crews will transition to East Gobbi Street and concrete crews will begin reconstructing sidewalks and ADA ramps on Main Street.

East Gobbi Street

Crews will begin water main construction on East Gobbi once tie-ins are complete on Main Street. During this time, East Gobbi will have intermittent lane closures on blocks with active construction (four to six weeks). Residents, emergency, and delivery vehicles have access at all times. Alternative routes are encouraged for through traffic during construction hours; East Gobbi will be reopened to two-way traffic at the end of each workday. 

The final part of this project before paving is the addition of storm drains along Perkins Street and improvements to the intersection at Perkins and Orchard Avenue. That work will begin this spring as crews are available.

Construction hours for all projects are Monday through Friday, 7 a.m. to 5:30 p.m.

For information on MTA buses, please call (707) 462-1422 or visit  www.Mendocinotransit.org; for more details on the construction project, please visit the webpage at  www.cityofukiah.com/ucrt.

Join the Conversation

1 Comment

  1. Wow. You mean a couple of streets are going to be repaved. What a shame. I thought Ukiah would never pave any of its not-so-charming potholed and fissure-ravaged streets at all. Where’d you get the money to do this?

Leave a comment

Your email address will not be published. Required fields are marked *