UKIAH, CA., 9/16/24 — Sewers are being replaced on Gobbi Street and environs. So are water lines. And so are sidewalks, with new curb ramps. Last Friday drivers weathered the closure on part of Perkins. That work is now done, and the focus shifts again to Gobbi.

On Gobbi west of State Street, concrete work on sidewalks continues, but two-way traffic should flow. East of State, the story is different. In some places and during some time frames, only west-bound traffic will be allowed.

Sewer work on the main line is expected to last through mid-October. Once the main line is in place, sewer laterals will need to be installed, and that will mandate full closure of some blocks during scheduled times. After all that, crews will return to Main Street to replace the water lines. That work is expected to go into the winter. Updated information is at www.cityofukiah.com/ucrt

See below for more information:

Please see the Urban Core Rehabilitation Transportation project construction update below:

Perkins Street:

  • On Friday (9/13), concrete work on Perkins Street will be completed. On Monday (9/16) crews will slurry seal in front of the Farm Supply which will require a limited one-lane closure in that block. Then work will be confined to Gobbi Street.

West Gobbi:

  • Concrete work will continue—the installation of new curb ramps and the replacement of sidewalks.  Two-way traffic will be allowed. 
  • AT&T will also be doing some work in this area that is unrelated to this project; however, it is not expected to impact traffic.

East Gobbi:

  • Sewer line replacement continues between Orchard and Leslie  –  westbound traffic only during work hours.
  • Beginning Tuesday, September 17th, sewer line crews move to the section between Leslie and Waugh Lane – two-way traffic, including turns to and from Waugh and Leslie allowed during this time.
  • Access to the MTA bus stops at Autumn Leaves, Post Office, Big Lots, and Social Security Office should also resume.  This section (Leslie-Waugh) is expected to take approximately one week. 
  • The next closure will be west of Waugh Lane, likely between Waugh and Main.  During this work, travel will once again only be allowed westbound.

Bigger picture—sewer work on Gobbi will continue through mid-October.  Once the mainline is done, crews will restart at Orchard and work westward to install sewer laterals.  Because the main line is on the south side of the street and many of the laterals are on the north side, this part of the work will require full closures of sections of Gobbi.  After Gobbi sewer is done, crews will return to Main Street to replace the water lines. (Sewer is already done.)  This work will continue through the winter.

You can find additional information about this project on our webpage: www.cityofukiah.com/ucrt.

Join the Conversation

4 Comments

  1. Thank you so much for posting this info! I appreciate the hard work that the road crews do, even though it’s inconvenient for the drivers…But it will be worth it in the long run. I always think of the “inconvenience” as a First World problem! We will survive!

  2. At no time in these articles about road work on these streets do they ever mention pedestrian crossings or walk ways. No one ever gives a thought or consideration to the pedestrians who need to access these roads. What are we to the city? Chopped liver.

  3. I am a Gobbi resident and this is the first of any info that has been shared!
    I was out of town and told to park on Oak and my car was towed and it cost 1564 to get it out of the impound,
    no one is talking about the inconvenience to the people who actually live on the street!

    I am happy for the new systems but not having any parking first from one side dedicated to a bike lane in front of my house then to these improvements
    it’s just too much!
    Help us help you by giving us the proper information and a place to park so we can get in and out of our homes UKIAH

  4. What a waste of money to pave Gobbi St. And now tear it up again to put sewer lines in. Who plans all this waste of money?